2017 Well Tank Replacement Schedule

Tentative schedule for the well tank replacement project:

June 26 — Advertise for Construction Bids

July 10 — Receive and Open Construction Bids.

July 17 — Award Construction Bid

July 24 – Aug 18 — Shop Drawings

Aug 21 – Sept 29 — Tank Fabrication

Oct 2 – Oct 20 — Tank Delivery and Erection

Oct 23 – Oct 27 — System Start Up