2018 Tank Installation Schedule

West Shore Park Water Tank Project

Spring 2018

(subject to weather conditions)

Start

Finish

Set up temporary water system

Mon 3/19

Fri 4/6

Demolish existing tank

Mon 4/9

Fri 4/13

Form and pour new tank base

Mon 4/16

Fri 4/27

Install new tank

Mon 4/30

Fri 5/18

Disinfect system

Mon 5/21

Wed 5/23

Online with new tank

Thur 5/24

Thur 5/24

Remove temporary system

Fri 5/25

Mon 5/28

Landscaping

Tue 5/29

Thur 5/31

Clean up and demobilize

Tue 5/29

Tue 5/29

Completion

Wed 5/30

Wed 5/30